SubjectOrder — Certificate of Public Convenience and Necessity GC-127 to NOVA Gas Transmission Ltd., in respect of the proposed construction and operation of the NGTL Towerbirch Expansion Project
PrecisOrder directing the National Energy Board to issue a CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY GC-127 to NOVA Gas Transmission Ltd.(NGTL) in order to authorize the construction and operation of the NGTL Towerbirch Expansion Project.
RegistrationRegistration:  SI
Attachments1-OIC / DDC 
 
 2016-11622016-12-16NRCAN
ActNational Energy Board Act
SubjectExtending the time limit - NGTL Towerbirch Expansion Project proposed by NOVA Gas Transmission Ltd.
PrecisOrder extending the legislated time limit for the National Energy Board in respect of the NGTL TOWERBIRCH EXPANSION PROJECT proposed by NOVA GAS TRANSMISSION LTD. by three months.
Attachments1-OIC / DDC 
 
 2016-11182016-12-09NRCAN
ActNational Energy Board Act
SubjectAmending Order AO-002-GC-125 - NOVA Gas Transmission Ltd.
PrecisOrder approving the ISSUANCE by the National Energy Board of Amending Order AO-002-GC-125 to NOVA GAS TRANSMISSION LTD (NGTL) in order to stimulate development in the North Montney natural gas basin and support the Canadian natural gas market by offering a transportation link to the liquefied natural gas (LNG) industry in Canada, and enhance Canada's economic prosperity.
Attachments1-OIC / DDC 
 
 2016-09622016-10-28NRCAN
ActCanadian Environmental Assessment Act
National Energy Board Act
SubjectCertificate of Public Convenience and Necessity GC-126 for the 2017 NGTL System Expansion Project
PrecisOrder directing the National Energy Board to issue a CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY GC-126 to NOVA Gas Transmission Ltd.(NGTL) in order to authorize the construction and operation of the 2017 NGTL System Expansion Project.
Attachments1-OIC / DDC 
 
 2016-05782016-06-17NRCAN
ActNational Energy Board Act
SubjectOrder extending the legislated time limit decision for NOVA Gas Transmission Ltd.’s - 2017 NGTL
PrecisOrder extending the legislated time limit for the Governor in Council decision for NOVA GAS TRANSMISSION LTD.’s proposed 2017 NGTL System Expansion Project by two months. The authority for extending the decision-making time limit is provided under subsection 54(3) of the National Energy Board Act.